Identification and Prioritization of Factors Causing Delays in ICT Projects Based on PMBOK Standards Using Fuzzy Delphi & Fuzzy Delphi Hierarchical Analysis

Authors

  • Seyed Saman Mirabdali Department of Industrial Engineering, Islamic Azad University of Masjid-i-Solieman, Iran
  • Reza Soltani Department of Industrial Engineering, Islamic Azad University of Masjid-i-Solieman, Iran

DOI:

https://doi.org/10.63053/ijmea.5

Keywords:

Project management, Delay, Fuzzy Delphi technique Analytical Hierarchy Process (FDAHP) Approach, ICT project

Abstract

Due to the importance of Information and Communication Technology (ICT) projects and lack of research on such projects in the petroleum industry, the present study mainly aimed to identify and prioritize the factors affecting the delay of ICT projects in Masjid-i-Solieman Oil and Gas Production Company as the case study. This investigation seeks the causes of undesirable conclusions of the ICT petroleum industry. The results are crucial to prevent the wastage of financial resources or time (due to sanctions and the difficulty of supply resources in Iran), also are very important for the project management of the oil and gas industry. On the other hand, it can be helpful all over the world.

According to the obtained prioritization, the most significant impact was the wrong sequence and definition of prerequisite relationships, prioritization instructions and lack of review of the priority in allocating limited resources to project components, and lack of timely allocation of financial resources, respectively, with the highest importance.

References

Clancy, T. (2008). The Standish Group Report. Chaos report retrieved. from:

https://www.standishgroup.com/sample-research-files/Haze4.pdf.

Cheng, CH-Hsue, Lin, Y. (2002). Evaluating the best main battle tank using fuzzy decision theory with linguistic criteria evaluation. European Journal of Operational Research, 142(1): 174-186. https://doi.org/10.1016/S0377-2217(01)00280-6

Farughi H, Alaniazar S, Mousavipour S.H., Moradi V. (2017). A practical framework based on Fuzzy FMEA to diagnose causes of delay in construction projects. Journal of Industrial Management Studies. 15(45):145-175. [Persian]

Garcia-Quevedo, J, Segarra-Blasco, A, Teruel, M. (2018). Financial constraints and failure of innovation projects. Https://dx.doi.org/10.1016/j.techfore.2017.05.029

Gholamnejad M, Norouzi MH, Norang A. (2017). Identifying and

ranking the failure factors of IT projects (Case study of Modbaran Amin Company). Fourth Global Conference on Advanced Progress in Engineering, Management, Economics, and Accounting.

Heilig L, Schwarze S, Voss S. (2018). An Analysis of Digital Transformation in the History and Future of Modern Ports. Intelligent Decision Support and Big Data for Logistics and Supply Chain Management. 13(2): 19-27.

Heim, I, Kalyuzhnova, Y, Li, W, Liu, K. (2019). Value co‐creation between foreign firms and indigenous small‐ and medium‐sized enterprises (SMEs) in Kazakhstan's oil and gas: The role of information technology spillovers. Thunderbird Int. Bus. Rev. 2019; 61: 911– 927. https://doi.org/10.1002/tie.22067

Iriarte C, Bayona S. (2020). IT projects success factors: a literature review. International Journal of Information Systems and Project Management, Vol. 8, No. 2, 2020, 49-78.

Kashiwagi, I. (2018). A Global Study on ICT Project Performance. Journal for the Advancement of Performance Information and Value, 10(1), 8 - 27. https://doi.org/10.37265/japiv.v10i1.19

Khansarizadeh S.H, Shirmohammadi M. (2015). Investigation and Prioritizing Outsourcing Of Information and Communication Technology (ICT) projects (Case study: ICT Infrastructure Projects). Journal of Information Technology Management. 7(22): 69 – 84.

Kumar Gupta, s. Gunasekaran, A. Antony,J. Gupta, S. Bag, S. (2019). Systematic literature of project failures: Current trends and scope for future research. Https://doi.org/10.1016/j.cie.2018.12.002

Liu YC, Chen CS. (2007). A new approach for application of rock mass classification on rock slope stability assessment. Eng Geol 89:129–143

Montequin, VR, Cousillas, SM, Alvarez, V, Villanueva, J. (2016). Success Factors and Failure Causes in Projects: analysis of cluster patterns using self-organizing maps. Conference on ENTERprise Information System / International Conference on Project MANagement / Conference on Health and Social Information System and Technologies / CENTERS / ProjMAN / HCist 2016, October 5-7.

Morcov S, Pintelon L, Kusters R. (2020). Definitions, characteristics, and measures of IT project complexity – a systematic literature review. International Journal of Information Systems and Project Management, Vol. 8, No. 2, 2020, 5-21

Olfat, L., Khosravani, F., Jalali, R. (2010). Identification and Ranking of Project Risk Based on PMBOK Standard by Fuzzy Approach. Industrial Management Studies, 8(19), 147-163.

Ozkan, S. Karabacak, B. (2010). Collaborative risk method for information security management practices: A case context within Turkey. International Journal of Information Management, 30:567-572.

Panahi J, Norouzi A. (2018). Investigation of risk management process and projects of Kermanshah Oil Company. organizational resource management research. 5:45-68. Procedia Computer Science. 121:224-231. Project Management Institute (2018). Pulse of the Profession 2018: Success in Disruptive Times – PMI.

Radgohar A, Motameni N. (2017). Classification of failure factors of oil industry construction projects based on project management standard using Shannon entropy and TOPSIS combined method. Journal of Science and Engineering Elites. 2(5): 118-134.

Tsiga Z, Emes M, Smith A. (2017). Critical success factors for projects in the petroleum industry. Https://doi.org/10.1016/j.procs.2017.11.031

Varajão J, Colomo-Palacios R, Silva H. (2017). ISO 21500:2012 and PMBoK 5 processes in information systems project management. Computer Standards & Interfaces. 50: 216-222.

Published

2023-12-01

How to Cite

Mirabdali, S. S., & Soltani, R. (2023). Identification and Prioritization of Factors Causing Delays in ICT Projects Based on PMBOK Standards Using Fuzzy Delphi & Fuzzy Delphi Hierarchical Analysis. International Journal of Applied Research in Management, Economics and Accounting, 1(1), 41–60. https://doi.org/10.63053/ijmea.5

Issue

Section

Articles